Skip to main content
District

Capital Project

Capital Project | Phoenix Central School District

Phoenix Central School District · Business Office

Capital Project

On October 9, 2024, residents approved a $46 million capital project. The improvements will address critical safety concerns, improve the efficiency of existing buildings, and upgrade several high-traffic areas, helping us maintain and improve our buildings and facilities.

  • $46 millionTotal project
  • October 9, 2024Approved by voters
  • No tax increaseThe project will not increase residents’ taxes
  • 4 sitesJCB, EJD, MAM, and the bus garage

2024 Capital Project

What the project includes

Work is planned at JCB, EJD, MAM, and the bus garage. Some of the improvements include:

  • All three schools

    Safety and systems

    • Install or enhance the lockdown emergency system
    • Update boilers
    • Address drainage needs
  • Grades 9–12

    JCB High School

    • Upgrade the kitchen and cafeteria
    • Upgrade the gym
    • Upgrade classrooms
  • Grades 5–8

    EJD Middle School

    • Upgrade special education classrooms
    • Upgrade the copy center
    • Upgrade kitchen equipment
  • Grades K–4

    MAM Elementary

    • Upgrade classrooms
    • Upgrade gym equipment
    • Improve outdoor safety

Capital Project 2024 Flyer (PDF) (opens in a new tab)

Progress

Project updates

Monthly updates on construction progress, schedules, and milestones.

Latest update

October 2026

Status as of

  • 11Complete
  • 5Nearly complete
  • 4In progress

Most Phase 1 work is now finished, including the EJD entrance and catch basins, new ventilation and temperature controls at EJD, the Transportation Center fuel island and bus lift, and tennis court lighting at JCB. Phase 2 renovations in the JCB 140 and 240 wings and the gymnasium are moving ahead.

Phase 1: Work by location

JCB High School

  • Park StreetComplete
  • Tennis court lightingComplete
  • Auditorium terrazzo floorComplete
  • Entry doorsNearly complete

    Entry doors are substantially complete. A few transom panels that arrived in the wrong size are being replaced, glass is on order, and the doors will then be connected to the lockdown system.

  • Gymnasium renovationsIn progress

    Backstops are complete and the new scoreboard and shot clocks are installed. Electrical connections are scheduled for this month.

  • Discus areaIn progress

    The old sod has been removed and grading is under way. New drainage and sod will follow.

EJD Middle School

  • Volney Street and entrance improvementsComplete
  • Catch basin repairsComplete
  • Home and careers and art room ventilationComplete
  • Data closet air conditioningComplete
  • Asbestos abatement and temperature controlsComplete
  • Athletic field improvementsNearly complete

    New sod is down and the walkway is paved. Final grading along the edges remains.

  • Boiler room renovationsNearly complete

    The new boilers are up and running and being fine-tuned. Ceiling patching and cleaning are in progress.

  • PA, clock, and lockdown systemIn progress

    Work is under way.

Transportation Center

  • Fuel islandComplete
  • Bus liftComplete
  • Emergency generatorComplete

    Final closeout paperwork is pending.

  • Driving lane expansionNearly complete

    Paving and the new sidewalk are complete. Crews are removing the old asphalt walk, grading, and seeding.

  • DoorsIn progress

    Refinishing is complete, and new door installation was scheduled for October 23.

MAM Elementary

  • PA, clock, and lockdown systemNearly complete

    Substantially complete. A few backordered speakers will be installed when they arrive.

Phase 2: JCB High School

  • 140 wing

    Old hallway walls have been removed. Crews are testing the floor slab for moisture, preparing the floor, and laying out the new walls.

  • 240 wing

    New classroom walls are framed and insulated, with electrical boxes and wiring paths installed. Drywall is up, and fire caulking and painting are under way.

  • Gymnasium exterior

    New metal framing and exterior panels are going up.

  • Gymnasium interior

    Crews are hanging drywall and completing electrical work behind the bleachers.

  • Wrestling room and gym mechanical room

    Walls are being insulated and drywalled.

Photos from October

Project documents

Completed

2017 Capital Project

About the completed 2017 project

Phoenix Central School District officials joined representatives from King & King Architects to celebrate the completion of capital project renovations that transformed classrooms, facilities, and grounds.

The original $38.2 million project was approved by district voters in 2017 and provided updated classrooms, a new athletic complex, a new auditorium, and 21st-century learning environments.

“Some of the project highlights include significant renovations at John C. Birdlebough High School, where some of the classrooms had not received significant improvements since 1955. Work at the high school included classroom upgrades to improve lighting and wiring; overhauling the auditorium; building a 2,000 square-foot addition to relocate the band and chorus rooms; upgrading technology; replacing windows and the roof; building a new wrestling room and athletic storage area; and creating a synthetic turf stadium, complete with new lighting.”

Karl Seckner, then Assistant Superintendent of Finance & Educational Services

In addition to the initial work, the district used $2.6 million in voter-approved capital reserve funds to cover other sitework and interior renovations at each building. That smaller project, approved in 2019, provided improved parent drop-off and pick-up systems at all three schools, a new playground at MAM, a renovated elevator at JCB, and classroom floor replacement.

All the work was done at no additional cost to taxpayers, as both projects were funded through a combination of reserves, state aid, and retiring debt.

“Thanks to careful fiscal planning, we were able to complete these much-needed upgrades at zero tax impact. This project has been transformative in every sense of the word. Phoenix schools now have some of the best state-of-the-art classrooms and facilities in CNY. I would personally like to thank the entire Phoenix CSD community for their support of these projects.”

Christopher Byrne, then Superintendent

District officials and representatives from King & King Architects at the celebration marking completion of the 2017 capital project

2017 project documents