Latest update
October 2026
Status as of
- 11Complete
- 5Nearly complete
- 4In progress
Most Phase 1 work is now finished, including the EJD entrance and catch basins, new ventilation and temperature controls at EJD, the Transportation Center fuel island and bus lift, and tennis court lighting at JCB. Phase 2 renovations in the JCB 140 and 240 wings and the gymnasium are moving ahead.
Phase 1: Work by location
JCB High School
- Park StreetComplete
- Tennis court lightingComplete
- Auditorium terrazzo floorComplete
- Entry doorsNearly complete
Entry doors are substantially complete. A few transom panels that arrived in the wrong size are being replaced, glass is on order, and the doors will then be connected to the lockdown system.
- Gymnasium renovationsIn progress
Backstops are complete and the new scoreboard and shot clocks are installed. Electrical connections are scheduled for this month.
- Discus areaIn progress
The old sod has been removed and grading is under way. New drainage and sod will follow.
EJD Middle School
- Volney Street and entrance improvementsComplete
- Catch basin repairsComplete
- Home and careers and art room ventilationComplete
- Data closet air conditioningComplete
- Asbestos abatement and temperature controlsComplete
- Athletic field improvementsNearly complete
New sod is down and the walkway is paved. Final grading along the edges remains.
- Boiler room renovationsNearly complete
The new boilers are up and running and being fine-tuned. Ceiling patching and cleaning are in progress.
- PA, clock, and lockdown systemIn progress
Work is under way.
Transportation Center
- Fuel islandComplete
- Bus liftComplete
- Emergency generatorComplete
Final closeout paperwork is pending.
- Driving lane expansionNearly complete
Paving and the new sidewalk are complete. Crews are removing the old asphalt walk, grading, and seeding.
- DoorsIn progress
Refinishing is complete, and new door installation was scheduled for October 23.
MAM Elementary
- PA, clock, and lockdown systemNearly complete
Substantially complete. A few backordered speakers will be installed when they arrive.
Phase 2: JCB High School
- 140 wing
Old hallway walls have been removed. Crews are testing the floor slab for moisture, preparing the floor, and laying out the new walls.
- 240 wing
New classroom walls are framed and insulated, with electrical boxes and wiring paths installed. Drywall is up, and fire caulking and painting are under way.
- Gymnasium exterior
New metal framing and exterior panels are going up.
- Gymnasium interior
Crews are hanging drywall and completing electrical work behind the bleachers.
- Wrestling room and gym mechanical room
Walls are being insulated and drywalled.